File #: 2021-966    Version: 1 Name:
Type: Consent Status: Agenda Ready
File created: 12/15/2021 In control: City Council
On agenda: 1/4/2022 Final action:
Title: CONSIDER APPROVAL OF PLANS, SPECIFICATIONS AND ESTIMATES, AND AUTHORIZATION TO ADVERTISE FOR CONSTRUCTION BIDS FOR PROJECT NO. 1393-4: CITYWIDE ANNUAL OVERLAY PROGRAM AND PROJECT NO. 1411-4: CITYWIDE ANNUAL CONCRETE REPLACEMENT PROGRAM FOR MAIN STREET FROM CARSON STREET TO VICTORIA STREET (CITY COUNCIL)
Attachments: 1. 1393-4 - Exhibit 1 - Location Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Report to Mayor and City Council
Tuesday, January 04, 2022
Consent


SUBJECT:
Title
CONSIDER APPROVAL OF PLANS, SPECIFICATIONS AND ESTIMATES, AND AUTHORIZATION TO ADVERTISE FOR CONSTRUCTION BIDS FOR PROJECT NO. 1393-4: CITYWIDE ANNUAL OVERLAY PROGRAM AND PROJECT NO. 1411-4: CITYWIDE ANNUAL CONCRETE REPLACEMENT PROGRAM FOR MAIN STREET FROM CARSON STREET TO VICTORIA STREET (CITY COUNCIL)

Body
I. SUMMARY

The Plans, Specifications, and Estimates (PS&E) for Project No. 1393-4: Citywide Annual Overlay Program and Project No. 1411-4: Citywide Annual Concrete Replacement Program for FY 2021/22 for Main Street from Carson Street to Victoria Street have been completed and are ready for construction bids (Exhibit No. 1). To maximize economies of scale, the two projects, asphalt street work and sidewalk concrete work, have been combined and the estimated construction cost totals $3,500,000.00.
It is requested that the City Council approve the PS&E for the combined projects and authorize staff to advertise for construction bids.


II. RECOMMENDATION
Recommendation

TAKE the following actions:
1. APPROVE the plans, specifications, and estimates, and order the work for Project No. 1393-4: Citywide Annual Overlay Program and Project No. 1411-4: Citywide Annual Concrete Replacement Program for FY 2021/22 for Main Street from Carson Street to Victoria Street.
2. AUTHORIZE staff to advertise the work and call for construction bids for Project No. 1393-4: Citywide Annual Overlay Program and Project No. 1411-4: Citywide Annual Concrete Replacement Program for FY 2021/22 for Main Street from Carson Street to Victoria Street.



Body
III. ALTERNATIVES

1. DO NOT APPROVE the PS&E and the call for bids.
2. TAKE another action the City Council deems appropriate, consistent with the requirements of the law.


IV. BACKGROUND

Each year the City performs pavement overlay and concrete replacement work and makes its best effort to implement the street repair and rehabilitation need...

Click here for full text