CONSIDER APPROVAL OF PLANS, SPECIFICATIONS AND ESTIMATES, AND AUTHORIZATION TO ADVERTISE FOR CONSTRUCTION BIDS FOR PROJECT NO. 1621: SEPULVEDA BLVD STREET IMPROVEMENT FROM MAIN STREET TO AVALON BOULEVARD (CITY COUNCIL)
Body
I. SUMMARY
Project No. 1621: Sepulveda Boulevard Street Improvement from Main Street to Avalon Boulevard is listed in the City's Capital Improvement Program (CIP) (Exhibit No. 1). This project will be funded by Measure R and Measure M.
The project includes pavement rehabilitation, tree removal and replacement, and concrete reconstruction (such as curb, gutter, driveway approaches and sidewalks).
The Plans, Specifications, and Estimates (PS&E) for the improvements for Project No. 1621: Sepulveda Boulevard Street Improvement from Main Street to Avalon Boulevard have been completed and are ready for construction bids. The PS&E are on file in the City Engineer's Office. The estimated construction cost is $1,226,614.00.
It is requested that the City Council approve the PS&E and authorize staff to advertise for construction bids.
II. RECOMMENDATION
Recommendation
TAKE the following actions:
1. APPROVE the plans, specifications, and estimates, and order the work for Project No. 1621: Sepulveda Boulevard Street Improvement from Main Street to Avalon Boulevard for FY 2021/22.
2. AUTHORIZE staff to advertise the work and call for construction bids for Project No. 1621: Sepulveda Boulevard Street Improvement from Main Street to Avalon Boulevard.
Body
III. ALTERNATIVES
1. DO NOT APPROVE the PS&E and the call for bids.
2. TAKE another action the City Council deems appropriate, consistent with the requirements of the law.
IV. BACKGROUND
Project No. 1621: Sepulveda Boulevard Street Improvement from Main Street to Avalon Boulevard is listed in the city's Capital Improvements Program (CIP). This project is programmed for FY 2021/22 funded by Measure R ...