Title: CONSIDER APPROVAL OF THE PLANS, SPECIFICATIONS, AND ESTIMATES FOR PROJECT NO. 1628: TRAFFIC SIGNAL INSTALLATION AT THE INTERSECTION OF TAJAUTA AVENUE AND DEL AMO BOULEVARD, AND AUTHORIZE STAFF TO ADVERTISE FOR CONSTRUCTION BIDS (CITY COUNCIL)
Attachments: 1. Exhibit No. 1 - Location Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Report to Mayor and City Council
Tuesday, October 06, 2020
Consent


SUBJECT:
Title
CONSIDER APPROVAL OF THE PLANS, SPECIFICATIONS, AND ESTIMATES FOR PROJECT NO. 1628: TRAFFIC SIGNAL INSTALLATION AT THE INTERSECTION OF TAJAUTA AVENUE AND DEL AMO BOULEVARD, AND AUTHORIZE STAFF TO ADVERTISE FOR CONSTRUCTION BIDS (CITY COUNCIL)

Body
I. SUMMARY

Project No. 1628: Traffic Signal Installation at the intersection of Tajauta Avenue and Del Amo Boulevard is included in the City's Capital Improvement Program (CIP) list. Progress has been made and the project plans, specifications, and estimates (PS&E) that were prepared by P.A. Arca Engineering, Inc. are available for review in the City Engineer's Office. The project is now ready for construction bid with a total estimated construction cost of $230,000.00.
This project is subject to the requirement of the City's Master Project Labor Agreement (PLA) and the City's Enhanced Electrical Safety Policy (EESP). The selected contractor and all subcontractors have an obligation to comply with the terms of the PLA and the EESP.
Staff requests that City Council approve the PS&E and authorize staff to advertise this project for construction bids.


II. RECOMMENDATION
Recommendation

TAKE the following actions:

1. APPROVE the Plans, Specification and Estimates for Project No. 1628: Traffic Signal Installation at the intersection of Tajauta Avenue and Del Amo Boulevard.

2. AUTHORIZE staff to advertise the work and call for construction bids.
1.

Body
III. ALTERNATIVES

1. DO NOT APPROVE the above recommendations.
2. TAKE another action the City Council deems appropriate, consistent with the requirements of the law.


IV. BACKGROUND

The City's Capital Improvement Program (CIP) calls for the construction of Project No. 1628: Traffic Signal Installation at the intersection of Tajauta Avenue and Del Amo Boulevard (Exhibit No. 1).
Tajauta Avenue is a 40-foot wide local street with one travel lane in each direction, provides no...