Title: CONSIDER APPROVAL OF THE PLANS, SPECIFICATIONS, AND ESTIMATES FOR PROJECT NO. 1422: BROADWAY INTERSECTION IMPROVEMENTS - TRAFFIC SIGNAL MODIFICATIONS, AUTHORIZE STAFF TO ADVERTISE FOR CONSTRUCTION BIDS, AND APPROVE AMENDMENT TO THE FUNDING AGREEMENT WITH LOS ANGELES COUNTY METROPOLITAN TRANSPORTATION AUTHORITY (CITY COUNCIL)
Attachments: 1. Exhibit No. 1 - LocationMap.pdf, 2. Exhibit No. 2 - LACMTA Amendment No2.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Report to Mayor and City Council

Tuesday, February 04, 2020

Consent

 

 

SUBJECT:                     

Title

CONSIDER APPROVAL OF THE PLANS, SPECIFICATIONS, AND ESTIMATES FOR PROJECT NO. 1422: BROADWAY INTERSECTION IMPROVEMENTS - TRAFFIC SIGNAL MODIFICATIONS, AUTHORIZE STAFF TO ADVERTISE FOR CONSTRUCTION BIDS,  AND APPROVE AMENDMENT TO THE FUNDING AGREEMENT WITH LOS ANGELES COUNTY METROPOLITAN TRANSPORTATION AUTHORITY  (CITY COUNCIL)

 

Body

I.                     SUMMARY

Project No. 1422: Broadway Intersection Improvements - Traffic Signal Modifications is included in the City’s CIP list (Exhibit No. 1). The Los Angeles County Metropolitan Transportation Authority (LACMTA) is providing reimbursable grant funds in the amount of $528,638 for this project. Progress has been made, and the project plans, specifications, and estimates (PS&E) that were prepared by CNC Engineering, Inc. (CNC) are available for review in the City Engineer’s Office.

Based on the estimated project timeline, the funding agreement with LACMTA needs to be amended to extend the lapsing date through February 28, 2021. (Exhibit No 2).

 

II.                     RECOMMENDATION

Recommendation

TAKE the following actions:

 

1.                     APPROVE the Plans, Specification and Estimates for Project No. 1422: Broadway Intersection Improvements - Traffic Signal Modifications.

 

2.                     AUTHORIZE staff to advertise the work and call for construction bids

 

3.                     AUTHORIZE the City Manager to sign Amendment No. 2 - Funding Agreement CFP ID#F7322 - Broadway Intersection Improvements - Traffic Signal Modifications between the City of Carson and Los Angeles County Metropolitan Transportation Authority.

 

1.                     

Body

III.                     ALTERNATIVES

1.                     DO NOT APPROVE the above recommendations.

2.                     TAKE another action the City Council deems appropriate, consistent with the requirements of the law.

IV.                     BACKGROUND

The City’s Capital Improvement Program (CIP) calls for the construction of Project No. 1422: Broadway Intersection Improvements - Traffic Signal Modifications. 

The project will improve the operation, efficiency, and visibility of five signalized intersections that are located on Broadway between Alondra Boulevard and Victoria Street. Broadway is a major north-south four lane arterial truck route that is adjacent to heavy and light industrial land uses with some commercial establishments.  The length of the corridor is 1.5 miles and the signalized intersections include the following locations:

1.                     Alondra Boulevard at Broadway

2.                     Gardena Boulevard at Broadway

3.                     Albertoni Street at Broadway

4.                     Pedestrian Crossing (south of Albertoni Street) at Broadway

5.                     Victoria Street at Broadway

The City retained CNC to prepare the PS&E for this project, and this work has been completed and is consistent with staff’s requirements.

The anticipated timeline for this project is as follows:

Preparation of Plans, Specifications, and Estimates 

Completed

Advertise Notice Inviting Bids

March 2020

Award of Construction Contract

 April/May  2020

Start of construction

June/July  2020

Completion of construction

December 2020

Project Close-Out

February 2021

 

V.                     FISCAL IMPACT

This project is partially funded by a reimbursable grant through LACMTA in the amount of $528,638 and by Measure R local funds in the amount of $284,651.

It is anticipated that additional funding in the amount of approximately $408,000 will be needed to cover the total project cost. After construction bids are received, staff will return to City Council to amend the City’s budget and to award a construction contract.

 

Anticipated project costs: 

Description

Estimated Project Cost

Design (CNC Engineering)

$50,320

Design Contingency (10%)

$5,032

Construction (TBD)

$1,000,000

Construction Contingency (15%)

$150,000

SCE Fees

$15,000

Publication / Printing

$500

Total

$1,220,852

 

VI.                     EXHIBITS

1. Location Map.  (pg. 4)

2.                      Amendment No. 2 - Funding Agreement CFP ID#F7322 - Broadway

Intersection Improvements - Traffic Signal Modifications between the City of Carson and Los Angeles County Metropolitan Transportation Authority Agreement.  (pgs. 5-8)                     

Prepared by:  Reata Kulcsar, Sustainability Administrator - Utilities