File #: 2019-413    Version: 1 Name:
Type: Consent Status: Agenda Ready
File created: 4/15/2019 In control: City Council
On agenda: 5/7/2019 Final action:
Title: CONSIDER APPROVAL OF PLANS, SPECIFICATIONS AND ESTIMATES, AND AUTHORIZATION TO ADVERTISE FOR CONSTRUCTION BIDS FOR PROJECT NO. 1393-2: CITYWIDE ANNUAL OVERLAY PROGRAM AND PROJECT NO. 1411-2: CITYWIDE ANNUAL CONCRETE REPLACEMENT PROGRAM (CITY COUNCIL)
Sponsors: Public Works
Attachments: 1. EXH. No. 1 Project 1411-2 1393-2_.pdf, 2. EXH. No. 2 SEPULVEDA Blvd. AC PCC Replacement QUANTITES_.pdf, 3. EXH. No. 3 Del Amo Proj. 1393 & 1411.pdf, 4. EXH. No. 4 Annual Concrete Proj1392_.pdf, 5. EXH. No. 5 Avalon Proj1444.pdf, 6. EXH. No. 6 Turmont St. Location Map Proj No.1547.pdf
Report to Mayor and City Council
Tuesday, May 07, 2019
Consent


SUBJECT:
Title
CONSIDER APPROVAL OF PLANS, SPECIFICATIONS AND ESTIMATES, AND AUTHORIZATION TO ADVERTISE FOR CONSTRUCTION BIDS FOR PROJECT NO. 1393-2: CITYWIDE ANNUAL OVERLAY PROGRAM AND PROJECT NO. 1411-2: CITYWIDE ANNUAL CONCRETE REPLACEMENT PROGRAM (CITY COUNCIL)

Body
I. SUMMARY

The plans, specifications and estimates (PS&E) for Project No. 1393-2: Citywide Annual Overlay Program, and Project No. 1411-2: Citywide Annual Concrete Replacement Program for FY 2018/19 have been completed and are ready for construction bids (Exhibit Nos. 1 and 2). To maximize economies of scale, the two projects have been combined, and the estimated construction cost totals $1,112,000.00.
It is requested that the City Council approve the PS&E for the combined projects, and authorize staff to advertise for construction bids.

II. RECOMMENDATION
Recommendation

TAKE the following actions:
1. APPROVE the plans, specifications and estimates, and order the work for Project No. 1393-2: Citywide Annual Overlay Program and Project No. 1411-2: Citywide Annual Concrete Replacement Program for FY 2018/19.
2. AUTHORIZE staff to advertise the work and call for construction bids for Project No. 1393-2: Citywide Annual Overlay Program and Project No. 1411-2: Citywide Annual Concrete Replacement Program for FY 2018/19.


Body
III. ALTERNATIVES

1. DO NOT APPROVE the PS&E and the call for bids.
2. TAKE another action the City Council deems appropriate, consistent with the requirements of the law.

IV. BACKGROUND

Each year the City performs pavement overlay and concrete replacement work, and makes its best effort to implement the street repair and rehabilitation needed in order to maintain the integrity of the City's infrastructure. Selection of street projects is based on the data contained in the City's Pavement Management Program (PMP). Each street segment in the PMP is assigned a corresponding Pavement Condition Index (...