File #: 2018-480    Version: 1 Name:
Type: Discussion Status: Agenda Ready
File created: 6/20/2018 In control: Successor Agency
On agenda: 7/17/2018 Final action:
Title: CONSIDERATION TO ACCEPT AS COMPLETE PROJECT NO. 1043: CARSON STREET MASTER PLAN (SUCCESSOR AGENCY)
Attachments: 1. Location Map, 2. File Summary
Report to Successor Agency
Tuesday, July 17, 2018
Discussion


SUBJECT:
Title
CONSIDERATION TO ACCEPT AS COMPLETE PROJECT NO. 1043: CARSON STREET MASTER PLAN (SUCCESSOR AGENCY)

Body
I. SUMMARY

Project No. 1043: Carson Street Master Plan has been completed in accordance with approved plans and specifications. It is requested that the Carson Successor Agency (CSA) accept the work as complete and authorize staff to file the Notice of Completion with the Los Angeles County Registrar-Recorder / County Clerk Office.

II. RECOMMENDATION
Recommendation

TAKE the following actions:
1. ACCEPT as complete Project No. 1043: Carson Street Master Plan.
2. AUTHORIZE staff to file a Notice of Completion.


Body
III. ALTERNATIVES

1. DO NOT ACCEPT the project as complete. However, Civil Code Section 3093 requires a Notice of Completion to be filed for record within 10 days, upon the completion and settlement of all public works project claims, if any.
2. TAKE another action the Agency deems appropriate and consistent with the requirements of the law.

IV. BACKGROUND

The City's Capital Improvement Program (CIP) called for the construction of Project No. 1043: Carson Street Master Plan. The project consists of streetscape improvements within the Carson Street Corridor, a 1.75 mile stretch of roadway between the I-405 and the I-110 freeways, and the enhancement of the landscaping and other features on Avalon Boulevard from the I-405 freeway to 220th Street (Exhibit No. 1). The scope of work included, but was not limited to:
1. Installation of new, colorful, drought-tolerant landscaping at parkways and medians.
2. Installation of street furniture; such as benches, trash receptacles, bike racks, and pedestrian lights.
3. Installation of seating nodes for pedestrian rest areas.
4. Reconstruction of driveways
5. Installation of traffic signals.
6. Installation of ADA compatible bus shelters.
7. Installation of decorative crosswalks to enhance major intersections.
8...

Click here for full text