I. SUMMARY
This action would approve an additional amount of funding for the Professional Services Agreement with RE|Solutions, LLC (RES), increasing the contract amount by $25,571.48. The Board approved an Environmental Risk Manager contract with RES at a Special Meeting on June 21, 2017, but the drafting and execution of the final version of the contract was more complex than anticipated, and the overall project schedule could not bear a stoppage of work by RES during this period. Staff recommended the Contractor continue to work under the terms of the existing contract until the new contract is executed. On August 7 the Board approved extending the contract until the end of July and expanding the budget to $400,000, but in the reconciliation of the PO the contract is short by $25,571.48. This action would allow the contract to be fully paid and close. It does not affect the current Risk Manager Contract with RES, which is still in effect.
II. RECOMMENDATION
Recommendation
TAKE the following actions:
1. APPROVE Amendment No. 3 to a Professional Services Agreement with RE|Solutions, LLC for environmental regulatory and project management services, increasing the contract amount by $25,571.48 to $425,571.28.
2. AUTHORIZE the Chairman to execute the agreement in a form approved by Authority Counsel.
Body
III. ALTERNATIVES
TAKE any other action the Reclamation Authority Board deems appropriate.
IV. BACKGROUND
In November, 2016, the CRA and RES entered a contractual services agreement (Agreement) where RES would provide certain assistance to the CRA, including with the Tetra Tech termination, negotiation with DTSC over new financial assurance, develo...