File #: 2023-0873    Version: 1 Name:
Type: Consent Status: Agenda Ready
File created: 11/13/2023 In control: City Council
On agenda: 12/5/2023 Final action:
Title: CONSIDER AWARD OF A CONSTRUCTION CONTRACT TO HZS ENGINEERING, INC. FOR PROJECT NO. 919: WILMINGTON AVENUE AND 223RD STREET - PULL BOX ACCESS IMPROVEMENTS (CITY COUNCIL)
Attachments: 1. Exhibit 1 - Project Location Map_IFB 23-03_PW No. 919, 2. Exhibit 2 - Bid Register Summary_IFB 23-03_PW No. 919, 3. Exhibit 3 - Public Works Contract HZS Construction Pull Boxes
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Report to Mayor and City Council
Tuesday, December 05, 2023
Consent


SUBJECT:
Title
CONSIDER AWARD OF A CONSTRUCTION CONTRACT TO HZS ENGINEERING, INC. FOR PROJECT NO. 919: WILMINGTON AVENUE AND 223RD STREET - PULL BOX ACCESS IMPROVEMENTS (CITY COUNCIL)

Body
I. SUMMARY

Project No. 919: Wilmington Avenue and 223rd Street Pull Box Access Improvements is part of the City of Carson (City's) Fiscal Year 2023/24 5-Year Capital Improvement Program (CIP) plan. This project includes site improvements to provide access to existing pull boxes necessary to maintain the traffic signal at the intersection of 223rd Street and Wilmington Avenue (Exhibit No. 1).
The project was advertised in a newspaper of local circulation and through the PlanetBids portal from October 19, 2023 to November 8, 2023. One (1) bid was received and opened at the City Clerk's Office. It was determined that HZS Engineering, Inc. was the lowest responsive and responsible bidder, with a total bid amount of $113,700.00.
Staff is requesting City Council to award a Construction Contract to HZS Engineering, Inc. for Project No. 919: Wilmington Avenue and 223rd Street Pull Box Access improvements for a not-to-exceed amount of $113,700.00. The total cost for this project including a 10% contingency is $125,070.00

II. RECOMMENDATION
Recommendation

TAKE the following actions:
1. AWARD a Construction Contract to HZS Engineering, Inc., the lowest responsive and responsible bidder, for Project No. 919: Wilmington Ave and 223rd Street - Pull Box Access Improvements, in the not to exceed amount of $113,700.00.
2. AUTHORIZE the expenditure of construction contingencies in the amount of $11,370.00 (10%) for change orders and any unforeseen construction work such as substructure conflicts, contaminated soil removal and disposal, material testing, and other work that may be necessary to complete this project.
3. AUTHORIZE the Mayor to execute a Construction Contract with HZS Engineering Inc., following approva...