File #: 2023-0326    Version: 1 Name:
Type: Consent Status: Agenda Ready
File created: 4/24/2023 In control: City Council
On agenda: 9/19/2023 Final action:
Title: CONSIDER REJECTION OF BIDS FOR IFB 23-03, PROJECT NO. 919: WILMINGTON AVENUE AND 223RD STREET - ACCESS TO PULL BOXES (CITY COUNCIL)
Attachments: 1. Exhibit 1 - Project Location Map for Project No. 919, 2. Exhibit 2 - Bid Register for IFB 23-03
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Report to Mayor and City Council
Tuesday, September 19, 2023
Consent


SUBJECT:
Title
CONSIDER REJECTION OF BIDS FOR IFB 23-03, PROJECT NO. 919: WILMINGTON AVENUE AND 223RD STREET - ACCESS TO PULL BOXES (CITY COUNCIL)

Body
I. SUMMARY

Project No. 919: Wilmington Ave & 223rd St. Access to Pull Boxes is part of the Public Works Capital Improvement Program which includes site improvements within the Dominguez Channel at the Southwest corner of 223rd/Wilmington Avenue. The site improvements include providing access to existing pull boxes that are necessary to maintain the traffic signal at the intersection of 223rd Street and Wilmington Avenue.
The project was advertised in a newspaper of local circulation and through the PlanetBids portal from March 9, 2023, to April 6, 2023. One (1) bid was received and opened at the City Clerk's Office. Public Works Engineering determined that CWS Systems was the lowest responsive and responsible bidder, with a total bid amount of $203,000.00.
Given that only one bid was received, staff is recommending that City Council reject the bid submitted by CWS Systems Inc. and re-advertise the Project with a wider outreach to secure more competitive bids.

II. RECOMMENDATION
Recommendation

Take the following actions:

1. REJECT the bids received for IFB 23-03 Project No. 919 - Wilmington Ave & 223rd St. Access to Pull Boxes

2. AUTHORIZE staff to re-advertise the project for construction bid in an effort to receive more competitive bid amounts.

Body
III. ALTERNATIVES

1. DO NOT reject the bid.
2. TAKE another action the City Council deems necessary and appropriate at this time consistent with the requirements of the law.


IV. BACKGROUND

Project No. 919: Wilmington Avenue and 223rd Street - Access to Pull Boxes is included in the City's Capital Improvement Program (CIP) list.
In 2019, the City of Carson completed the freeway interchange project at the 405 Freeway and Wilmington Avenue. During construction, the contractor inst...